EDVY Closes April 26th! Enter Now Top Link
Home > Latest   +   Structures

UMA Preserves Vital Retaining Wall Structures for N.C. Bridge Demolition

UMA Preserves Vital Retaining Wall Structures for N.C. Bridge Demolition

Colfax, N.C. – UMA Geotechnical Construction, a North Carolina-based geotechnical contractor serving the Mid-Atlantic Region, this past May helped its customer avoid failure of retaining wall structures during the demolition of a bridge spanning Blanket Creek in the Winston-Salem area.

UMA, under its subcontract with Kernersville, North Carolina-based National Bridge Builders, installed 14 ground anchors on the two retaining walls that were being held in place by the span that was to be demolished and could have collapsed if not properly secured independently prior to demolition. Traffic had already been rerouted to the new replacement bridge.

“Throughout the duration of this project,” said UMA President Brian DeSpain, “UMA was faced with two main challenges in order to properly and safely install the anchors.”

First, the UMA crew had to attach the top of the anchors through the existing bridge deck in order to achieve the proper installation angle. The anchors could not be installed from below the bridge because that path was obstructed by the bridge itself.

UMA used duplex drilling to advance both casing and drill steel into each hole simultaneously to keep them from collapsing. After reaching the required 30- to 50-foot hole depth, UMA installed 30- to 54-foot anchors inside the steel casing, with lengths varied based upon location and bar sizes of either #6 or #11.

The bar system that UMA used also incorporated double corrosion protection, specifically Multiple Corrosion Protection (MCP) bars. This type of Class 1 corrosion protection consisted of a bare bar surrounded by a corrugated plastic sheath, which was large enough to allow it to be filled with grout and provided a three-inch solid casting of grout around all sides of the bar. After the hole was drilled to the proper depth, the bar and a tremie tube were placed into the hole, and the hole was completely grouted to the face of the wall.

After the proper grout curing time, the anchors were cyclically load-tested to the specified loads. At the end of the load tests, the anchors were locked off at 50 percent of the designed load in order to engage the anchor.

The second challenge was that the two retaining walls are positioned on either side of an active creek, fed by the nearby Lasater Mill Pond. To achieve the correct anchor installation position, UMA opted to use a semi-elevated platform constructed using crane mats. This allowed field technicians to use the appropriate drill angle while water flowed freely in the creek.

“The successful completion of any project relies on the management and technical skills of the construction team, both in the office and on site,” DeSpain said. “It’s because of the expertise and teamwork of the employees at UMA that the retaining walls were able to be properly secured, a critical step to a safe bridge demolition.”

An industry leader in the development and refinement of innovative polymer grouting techniques, UMA Geotechnical Construction, Inc. creates specialized solutions to assist clients with ground engineering needs that save money and minimize downtime. As one of the first to use lightweight structural polymers to improve subsurface soils at depths greater than 40 feet, UMA is uniquely equipped to deliver safe, predictable, and effective results. The team includes industry experts in structural support, earth retention, and soil stabilization with decades of experience, and is dedicated to ongoing advancement in the field.