The California Department of Water Resources provided a video update on construction work on the Oroville Spillways.

Crews work on the cut-off wall, installing the final rebar cages into the 80-foot holes and filling with concrete. Roller-compacted concrete (RCC) continues to be laid for the splashpad between the emergency spillway concrete weir and cut-off wall. Dental concrete is poured below the dentates of the main spillway for a new construction road.